Ambassador Bridge Bus Canopy

C.E. Gleeson ConstrucTors

DESCRIPTION

Technical Scope of Services provided for the Project.

· Daily coordination with Customs Border Patrol operations.

· Asphalt and concrete excavation for new foundations, piers, extended CBP booth islands and bollards.

· Concrete foundation, piers, island extensions and bollards.

· Structural steel erection.

· Metal standing seam roof erection.

· Cold-formed metal framing to connect new canopy to existing building and secondary inspection canopy.

· Electrical rework for new lighting and tube heaters.

· Tube heater installation at new canopy as well as adding them to the existing secondary inspection canopy.


DETAILS

Detroit, MI

Gleeson Personnel:

Project Manager:

Hannah Tache


Superintendent:

Matt Baglio


Project Engineer:

Josh Boers

Budget:

Initial: $641,000

Final: $752,413.31

Variance: +17%

There was a 111,000 CO for added scope that the Owner was originally handling.



3,120 Sq. Ft

Client:

Detroit International Bridge Company

Ken Carter, VP Construction